Project image: Albert Einstein Hospital
CASE 002

Healthcare · São Paulo

Albert Einstein Hospital

How to keep fabrication, construction, and operation aligned while implementing the new kitchen.

01

From factory to operation

P+A followed equipment fabrication and inspection, coordinated installation, and led commissioning. The work concluded with a dry run and operational team training.

FoodserviceHealthcareRetrofitProcurement

Advisory decisions

01

Fabrication under control

Pre-shipment inspections verified that the equipment matched the project specifications.

Inspection of professional kitchen equipment at the factory
02

Coordinated site installation

Weekly meetings aligned engineering, installers, and the hospital team with the assembly schedule.

Coordination of equipment installation on site
03

Commissioning and training

Functional testing and a dry run preceded training for the team responsible for the new kitchen.

Completed professional kitchen after the retrofit

Timeline

  1. 2017Technical assistance for equipment fabrication began.
  2. October 2017 to March 2018Weekly coordination of on-site installation.
  3. 2018Commissioning, dry run, and operational training.
04
Commissioned equipment and a team prepared to bring the new kitchen into operation.